Economic and dam related articles

Firm Gets Money for DOE Delays

by Staff and Wire Reports
Spokesman-Review, July 17, 2011

A federal court has awarded Energy Northwest $48.7 million in damages from the Department of Energy for delays in opening a Nevada nuclear repository.

The money reimburses Energy Northwest for building and licensing a used fuel storage area at the Columbia Generating Station in Richland.

The ruling came nearly five years after the U.S. Circuit Court of Appeals determined that DOE breached its contract for failing to accept the utility's used nuclear fuel.


Reuters Factbox: U.S. nuclear reactors similar to Fukushima

July 13 (Reuters) - The U.S. nuclear industry's top cop is to weigh major changes in how it regulates the country's 104 reactors after Japan's Fukushima disaster, a move that will help shape the future of the power source and could lead to significant cost increases.

A task force recommended the Nuclear Regulatory Commission look at a fundamental shift in how it plans for catastrophes like the earthquake and tsunami that swamped the Fukushima plant in March, the world's worst nuclear disaster in 25 years.

Now it is up to the five-member commission to decide which ideas to accept and how quickly to proceed in an industry where plant retrofits can run into the millions.

The NRC task force recommended requiring reliable hardened vent designs in boiling water reactors with the General Electric (GE.N) designed Mark I and Mark II containment types, the same as the damaged Fukushima reactors.

In the United States, 31 of the 104 operating reactors have the Mark I or Mark II containment type. The following lists those reactors, according to data from the NRC:

Reactor            Location            Size (MW)     Year    Design

ENERGY NORTHWEST
Columbia           Richland, WA          1190        1984    Mark II

TVA
Browns Ferry 1     Decatur, AL           1065        1974    Mark I
Browns Ferry 2     Decatur, AL           1104        1975    Mark I
Browns Ferry 3     Decatur, AL           1105        1977    Mark I
PROGRESS ENERGY (PGN.N)
Brunswick 1        Southport, NC          938        1977    Mark I
Brunswick 2        Southport, NC          920        1975    Mark I

NEBRASKA PUBLIC POWER DISTRICT
Cooper             Nebraska City, NE      770        1974    Mark I
EXELON (EXC.N)
Dresden 2          Morris, IL             867        1970    Mark I
Dresden 3          Morris, IL             867        1971    Mark I
LaSalle 1          Marseilles, IL        1118        1982    Mark II
LaSalle 2          Marseilles, IL        1120        1983    Mark II
Limerick 1         Limerick, PA          1134        1985    Mark II
Limerick 2         Limerick, PA          1134        1989    Mark II
Oyster Creek       Toms River, NJ         615        1969    Mark I
Peach Bottom 2     Lancaster, PA         1112        1974    Mark I
Peach Bottom 3     Lancaster, PA         1112        1974    Mark I
Quad Cities 1      Moline, IL             867        1972    Mark I
Quad Cities 2      Moline, IL             867        1972    Mark I

NEXTERA ENERGY (NEE.N)
Duane Arnold       Cedar Rapids, IA       580        1975    Mark I
SOUTHERN (SO.N)
Hatch 1            Baxley, GA             876        1975    Mark I
Hatch 2            Baxley, GA             883        1979    Mark I

DTE ENERGY (DTE.N)
Fermi 2            Monroe, MI            1122        1988    Mark I

PSEG (PEG.N)
Hope Creek         Hancock's Brdg, NJ    1161        1986    Mark I

ENTERGY (ETR.N)
Fitzpatrick        Oswego, NY             854        1976    Mark I
Pilgrim            Plymouth, MA           685        1972    Mark I
Vermont Yankee     Vernon, VT             620        1972    Mark I

XCEL (XEL.N)
Monticello         Monticello, MN         572        1971    Mark I

CONSTELLATION (CEG.N)
Nine Mile Point 1  Oswego, NY             621        1969    Mark I
Nine Mile Point 2  Oswego, NY            1140        1987    Mark II

PPL (PPL.N)
Susquehanna 1      Salem, PA             1149        1982    Mark II
Susquehanna 2      Salem, PA             1140        1984    Mark II
(Reuters Reporting by Eileen O'Grady in Houston, Roberta Rampton in Washington and Scott DiSavino in New York; Editing by Lisa Shumaker)

Staff and Wire Reports
Firm Gets Money for DOE Delays
Spokesman-Review, July 17, 2011